|


Gopal Daga, M.D.
Mundhra, Yogendra Prasad, Mohit
Saraf, Anil Sardana, Arun
Srivastava, A.J. Talaulicar,
T.N.Thakur
Gaps in
the Act... And some solutions
While the new Electricity
Act has elicited a mostly positive response,
industry experts feel there is room for
improvement. Some of the changes they
suggest are to free hydel generation from
the “license raj”, restrict the tenure of
regulatory commission members to one term,
and allow captive projects to sell power to
the SEBs and third parties without
preconditions. They also want a specific
time frame for introduction of open access
to T&D networks and for elimination of
cross-subsidies. We present their views…
Do you have any
suggestions for changes to the Electricity
Act, 2003? What provisions in the act need
further clarification from the government?
P.N. Bhandari
Partner, Paras Kuhad and Associates
(advocates)
The Electricity Act, 2003 is a big leap
towards modernization of the Indian power
sector. However, a statute is not and should
not be static document. It should have
adequate flexibility to remain a living
document. Based on actual experience, it may
have to be amended from time to time. Even
our Constitution has been amended more than
80 times.
The provision to liberate
generators from licensing is a bold and
welcome feature. I have repeatedly canvassed
that techno-economic clearance for private
generation projects is totally avoidable. A
company that is investing millions in
setting up a power plant is fully qualified
to assess whether the project is technically
sound and financially viable. But
surprisingly, for hydel projects we are
still clinging to the old and outdated
philosophy. There is no rationale for
excluding hydel projects from this
liberalization process. Rather the need for
liberalizing the hydel sector is much
greater because the ratio between thermal
and hydel generation is tilting against
hydel. Licensing has been dispensed within
the thermal sector because it was felt that
it leads to delay, to harassment and
possibly corruption. All these arguments are
equally valid for hydel projects. The only
objection could be that hydel projects may
involve construction of dams, etc., where
safety is very important. But the state
irrigation departments would in any case
look into the safety of such civil
structures and interception of water. The
risk, if any, is from civil construction,
which would be taken care of by the civil
engineering departments. No extra electrical
engineering risk is involved in hydel
projects compared to thermal projects.
Rather, the capacity of an average hydel
generating station is going to be much
smaller compared to an average thermal
station. Hence, there is no justification
for discriminating against hydel projects at
a time when the country needs to give a push
to hydel generation and other
non-conventional energy projects that are
eco-friendly and involve minimal recurring
costs and consequently reduced tariffs. In
order to give a boost to hydel generation it
should be equally liberated from the licence
raj.
Another provision that
needs a relook is the tenure of the
chairman/members of the regulatory
commission. Unlike the higher judiciary,
many of the regulatory commissions in the
infrastructure sector have yet to establish
their credentials for independence and
ability to withstand government pressures.
Very often the appointments in the
regulatory commissions reflect the
“flexibility” and “adjustability” of
superannuating civil servants in the eyes of
the government. Against this backdrop, there
should be no provision for grant of a second
term to such members. A term of three years
is too short to fully understand the system,
particularly for members who have no
background in the power sector. There should
be a one-time tenure of five or six years.
Once appointed, the chairman/members should
be totally immunized from government favours.
Under the present dispensation, while
considering cases for a second term, the
government is bound to evaluate the members’
performance in the light of whether they
have been “convenient” to the government or
not.
At the higher level, we
have been glibly talking of 100 per cent
metering. However, those associated with the
grassroots working of the electricity boards
would confirm that such a provision in
isolation can be counterproductive and
installation of a larger number of meters
may leed to lesser revenue. In the
agricultural sector particularly, a large
numbers of farmers either do not allow the
installation of meters to operate. Because
of this, the revenue from flat-rate
connections in the agricultural sector have
been substantially higher than that from
metered connections. Hence, meter
installation should be preceded by a
substantial increase in the minimum charges
so that even if some consumers damage the
meters, they will have to pay a
substantially higher minimum amount. Then
alone will the consumer appreciate that a
running meter is better than a stopped
meter.
In statutory matters,
there is very little scope for
“clarification” by the government. In actual
practice, if certain provisions turn out to
be problematic, the government should not
hesitate in amending the act from time to
time. Obsolescence in technology is well
known. We should be conscious about
obsolescence in laws also and be willing to
amend them promptly, whenever the need
arises, particularly during the initial
period.
Gopal Daga
Senior Executive, Shree Cement
My suggestions to make the Electricity
Act, 2003 more compatible in connection with
captive power projects (CPPs) are as under:
A CPP should be allowed
to sell its surplus power either to the
state electricity board (SEB) or to third
parties immediately without any
precondition. IN case the SEB is not willing
to buy the same, the CPP should be allowed
to sell the same to a third party at a
mutually agreed upon rate. The power should
be transmitted to the destination of use
through the state gridline and the state
compensated by paying wheeling charges. This
will allow the CPP full capacity utilization
as well as increase the availability of
power. This will create a win-win situation
for the state as well as for the captive
power producer and buyer.
M.D. Mundhra
Vice-President, Commercial, Malana
Power Company
The Electricity Act, 2003 is definitely
a step forward, but a lot more needs to be
done to give an impetus to the development
of hydel power, which has vast untapped
potential. This will require pragmatic and
transparent policies for allotment of hydel
power to the private sector and steps to
make the power cheaper. In order to achieve
this, we would suggest the following:
Delicensing: While
all other modes of power generation have
been delicensed in the Electricity Act, for
hydel power generation beyond a particular
capital expenditure, clearances from the CEA
continue to be mandatory. In our opinion,
since hydel power projects are capital
intensive, the capital cost limit beyond
which clearances should be made mandatory
should be Rs.10 billion. Hydel power
projects without any interstate issues
should be delicensed.
Allotment of hydel
projects: The act does not, in itself,
address the key issue of allotment of hydel
projects. As per the earlier policy, all
hydel projects below 100 MW could be
allotted on the MoU route and for projects
above 100 MW, competitive bidding was to be
followed. However, some states have
experimented with the competitive bidding
route for allotment of hydel projects below
100 MW also. By and large, such experiments
of inviting competitive bids based on
“royalty”, “upfront premium” or “rates of
power” have failed and allotment of hydel
projects to the private sector is
practically at a standstill. We suggest that
our of the 158 schemes covered in the prime
minister’s initiative of 50,000 MW, at least
95 projects below 200 MW covering 11,805 MW
should be earmarked for development by the
private sector. Feasibility reports for
these should be prepared e~editious1y and
those projects found viable should be
allotted in a transparent manner through a
two-stage bidding process without waiting
for detailed project reports. The basis of
the allocation of projects should be early
completion time, which, in turn, will fetch
more royalty to the states.
Reduction in cost of
hydel power: At present, power is
supplied at subsidised rates to cone class
of consumers, particularly for agriculture.
To offset this, power is supplied to
industries at high rates, which makes them
uncompetitive. Thus we are caught in a
vicious cycle. The solution lies not in
cross-subsidising one class of consumer by
charging more from another class, but in
taking steps to make the cost of power
cheaper at the source, that is, at the
generation level. We suggest the following
steps to reduce the cost of hydel
generation:
Rationalisation of
royalty: At present 12-15 per cent
royalty is charged from hydel projects. In
the case of coal, there is a royalty because
coal is consumed, but in the case of hydel,
water is only diverted, not consumed. As
such, there is no justification for charging
royalty save for the need of resources for
the development of hilly states. To balance
this, the royalty should be reduced to 6 per
cent in the first 15 years and increased to
18 per cent in the remaining years to make
hydel power economical without sacrificing
the interest of the state.
Waiver of customs and
excise duties: The mega power policy,
under which customs and excise duties have
been waived, should be extended to all power
plants irrespective of their size and
without any preconditions.
Creation of a hydel
power development fund: A 5 per cent
interest subside should be given to hydel
projects by creation of a hydel power
development fund on the pattern of the
Textile Upgradation Fund.
Incentive for peak
power generation: As is well known,
hydel power can cater to peak demands. To
provide incentive for peak generation, an
additional 15-25 per cent premium should be
provided on the normal tariff for generation
during the peak period.
Open access: It
seems that there will be multiple surcharges
at various stages of
transmission/distribution in case of open
access to consumers. The surcharge in lieu
of cross-subsidy needs to be capped. It
should not be more than 50 per cent of the
difference between the landed cost to the
industrial consumer, including the rate
negotiated by him with the generating
company and wheeling/transmission charges
and the rate being charged by the discoms
now.
Time limit for
abolition of cross-subsidy: There should
be a cap on the time during which a state
regulator should bring down the
cross-subsidy to zero. In our opinion, this
period should not be more than five years
and should be declared now so as to avoid
uneconomical investments in captive power.
Yogendra Prasad
CMD National Hydroelectric Power
Corporation
Yes, the following are the suggestions
for changes to the Electricity Act:
-
Generation has been delicensed. However,
hydroelectric schemes are to be
submitted to the Central Electricity
Authority (CEA) for concurrence but no
time-frame has been fixed for the
authority to issue concurrence. A time
frame should be specified.
-
Run-of-the-river schemes with
nonconsumptive use of water should be
kept free from the interstate angle.
-
The provision for exemption of
concurrence for hydro schemes by the CEA
below a certain amount of capital cost
as fixed by the union government should
be at par with the provision of other
statutory clearances to be issued by
government agencies like the Ministry of
Environment and Forests.
The provisions in the act
that need further clarification from the
government are:
One of the functions of
the state commission as specified in the
act is to regulate the electricity purchase
and procurement process of distribution
licensees, including the price at which
electricity is to be procured from the
generating companies, licensees or other
sources through agreements for purchase of
power for distribution and supply within the
state.
If the distribution
company purchases power from a generating
company whose tariff is determined by the
CERC, then the distribution company need not
get the purchase price approved by the SERC.
This will delay their power purchase
agreements with the generating companies.
This point needs clarification.
Mohit Saraf
Senior Partner, Luthra & Luthra, Law
Offices
And God said, “Let
there be light” and there was light. But the
electricity board said: ‘He would have to
wait until Thursday to be connected!”
Spike Milligan’s
“light-hearted” observation has little
comic connotation for the average Indian.
For decades, state-owned monopolies have
through sheer inefficiency crippled the
growth of the power sector. Hopefully, all
that is about to change — or so the preamble
to the act would have us believe.
The act has a laudatory
objective-promoting competition in the
electricity sector, rationalisation of
electricity tariff, protecting consumer
interests, et al. There is an insightful
observation that “we promise according to
our hopes and perform according to our
fears”. By analogy, while the preamble
offers many promises, the act itself
performs a remarkable act of self-sabotage.
In an attempted Japanese-style hara-kiri,
the act scuttles the very notions that it
ostensibly seeks to promote. Let us examine
how.
Captive question:
A captive generating plant as defined under
the act means a power plant set up by any
person to generate electricity primarily
for his own use and includes a power plant
set up by any cooperative society or
association of persons for generating
electricity primarily for use of the
members of such a cooperative society or
association.
However, it is not clear
whether a power plant set up through a
special purpose vehicle (SPV), that is an
incorporated body, for the use of the
shareholders of such SPV would fall under
the definition of captive generating plant.
This assumes added significance when we
consider that in order to shield a power
project from any unrelated liability, banks
and financial institutions would generally
prefer to finance a project undertaken by
any new SPV incorporated for that purpose.
It is advisable that the
said definition be amended to include
incorporated bodies. It is the hallmark of a
law well made that it recognises and
reflects elements of the economic reality
that it seeks to regulate.
Bungling on bundling: The
act provides that transmission licensees
cannot engage in trading activities. The
objective is to promote non-discriminatory
open access to transmission lines. This
well-intentioned provision, sadly, is doomed
to fail. The reason: a loophole that is
every businessman’s dream there is no
restriction on the common ownership of the
transmission and trading entities. The
absence of such a restriction would
immediately impact the proposed
“non-discriminatory open access” model.
This is especially
ironical since the act provides for
unbundling of the SEBs. The absence of a
restriction on common ownership would lead
to the bundling of transmission and trading
activities in the hands of private players.
It is highly recommended that the provisions
concerning transmission licensees
specifically provide that even the entities
under common ownership wilt not engage in
trading activity. Failure to do so might
mark an avoidable-and dangerous- shift from
public monopolies to private monopolies.
Open access: Open
access to transmission lines and
distribution networks is universally
regarded as the key to increasing
competition and ultimately promoting
consumer interest. Though the concept of
open access has been recognized in the act,
the state commission has been given the
power to introduce open access in successive
phases and subject to such conditions as it
may specify. Since no specific time-frame
has been provided for the introduction of
open access, this would doubtless cause
uncertainty and defer the much needed
investments in the capital starved power
sector. It is advisable that the act itself
specifies a common dead line (for all
states) for full implementation of open
access.
Cross-subsidy: One
of the central concerns of industrial and
commercial consumers of electricity has been
the issue of cross-subsidy provided by them
to agricultural and domestic users. Though
the act refers to the elimination of
cross-subsidy, it is conspicuously silent on
the mechanism and time-frame to be adopted.
In addition, the
surcharge under the act should merely cover
the cross-subsidy currently being provided.
It should not become a pretext for passing
on industry inefficiencies to the helpless
consumers.
Independence of
regulatory bodies: There are various
provisions in the act that could limit the
growth of an independent regulatory body, on
whose independence the entire growth and
development of the sector is dependent.
Hence, such provisions should be amended
keeping in view that the government, which
appoints and removes the regulator, is also
a dominant and incumbent player in the power
sector.
In conclusion, an
often-overlooked fact is that electricity is
a core infrastructure requirement for all
other industries, in addition to being
central to running commercial establishments
and simply ensuring a comfortable stay at
home. For interested parties, the act is not
a mere legislation but an act of faith that
the days of intermittent blackouts are
finally over. Amending the act suitably
would, hopefully, ensure just that.
Anil Sardana
Chief Executive Officer, North Delhi
Power Limited
As a distribution company, the act is a
welcome catalyst to promote competition in
distribution, which would force existing
companies to perform and improve asset
turnover and efficiencies. However, as
regards implementation in the true sense of
the framework contained in the act, one has
to wait for supplementary policy documents
such as a national tariff policy, national
electricity policy, national rural
electrification policy, and a policy on
criteria for award of additional
distribution licences. These documents are
being issued for discussion and debate to
get the views of stakeholders. Once the
entire policy documents and rules are in
place, the framework of the act will become
more credible.
Arun Srivastava
Managing Director, Essar Power
Limited
I have the following suggestions:
-
The act is silent on whether the power
purchase agreement (PPA) signed by the
SEBs prior to implementation of the act
would not be reopened by the SERC. This
has serious implications for those who
have invested a lot of money.
-
The act provides that generators can
sell power to bulk consumers subject to
levy of wheeling/transmission charges,
including surcharge in lieu of
cross-subsidy to be decided by the CERC/
SERC. I feel to make the state
government serious about phasing out
subsidies, the act should provide a cap
on the surcharge rate and time limit for
the phasing out instead of leaving it to
the SERCs to decide.
-
At present various state governments
levy different rates of electricity
duties on consumers. All the-good
intentions of the act would go to the
winds if this aspect is not covered. In
my opinion, the act should mention that
the rate of electricity duty would be
uniform through out the country or
would not be more than that prevailing
in each state before June 10, 2003.
-
The scope of captive generation has to
be clarified. Technically, as per the
present act, even houses/shops and
colony clusters can have captive
generation. Captive generation should be
limited to industrial activity and HT
consumers.
A.J. Talaulicar
President& Exec. Director, Power
Generation Business
and Cummins Diesel Sales and Services
(India) Limited
We are in the process of analysing the
implications of the new act with a number
of-external parties and refining our
business strategies. As such, I believe it
is somewhat premature to participate in a
group forum. However, the following are our
suggestions on the Electricity Act:
-
Early announcement of a fuel policy to
ensure longer-term predictability of
fuel costs without which no significant
private sector capacity investments
would take place due to the uncertainty.
-
The current move by some SEBs (such as
Andhra Pradesh and Tamil Nadu) to impose
electricity cess/duty even on captive
generation for own use will act as a
deterrent and is against the spirit of
the Electricity Act, which seeks to
encourage captive power capacity
addition.
-
A peculiar situation has arisen in
states like Gujarat where the SEBs are
returning captive power plant licence
requests to industries, directing them
to the SERCs, which say they do not know
how to go about the matter, This needs
to be addressed. There should be an
interim nationwide directive to all
states to allow users/industries to go
ahead with captive power plant
installation without licence hassles.
-
Use of standby power generation capacity
should be actively encouraged to aid in
curtailing the peak demand-supply gap by
providing incentives to users/industries
that go off the grid during peak demand
hours There should be stiffer
differential power tariffs during the
peak period. This would result in
efficient utilization of and investment
in overall power generation capacity.
-
Incentives should be provided for
distributed generation in rural areas,
for grid discipline, for usage of
non-conventional energy and for
cogeneration plants that help maximise
efficiency.
-
Environmentally responsible capacity
additions should be encouraged. And
penalties imposed for use of dirty fuels
to ensure a cleaner environment by
review and quicker implementation of
modified/ appropriate emission norms in
line with developed countries.
-
CPPs should be allowed to supply power
to an association of persons with a
third-party financier. Alternatively,
CPPs should be allowed to supply power
to any cluster of customers without any
additional surcharge. This will help
market forces operate to close the
capacity demand gap more efficiently.
-
Competition should be promoted to bring
down power costs to the end-user and
allow market forces to enforce
discipline on power providers. Increased
competition among power producers and
the play of market forces will allow
customers to demand quality power (at
right frequency and voltage), and
penalise players that are providing poor
quality power.
Clarity is required
on:
-
The definition of a CPP. Does the word
“primarily” mean 80 per cent of the
power generated or anything else?
-
Whether CPPs using dedicated
transmission lines also need to pay
surcharge towards subsidy.
-
Whether open access is subject to
availability. Does availability mean as
of arty particular moment/ day/month
/year?
T.N. Thakur
CMD, Power Trading Corporation
We are generally in agreement with the
framework of the act but we would like to
wait for the framework to be given body by
the regulatory commissions and the
policy-makers A lot of the legislation will
be given substance through case law, and we
would be keenly observing the developments
on this front. |