|

International Power
Finance Review
THE INDIAN POWER
SCENARIO: AN UPDATE
By Rajiv K. Luthra and S. Vyas,
Luthra & Luthra Law Offices
The electricity sector
in India has grown manifold, both in size
and capacity during the last 50 years. This
article sets out its development over that
time and looks at what is expected in the
future.
Generating capacity in
India has increased from a meagre 1,362 MW
in 1947 to above 85,744 MW in 1997.
Electricity generation, which was only 4.1
bn kWh in 1947 has risen to a level of over
394bn kWh in 1996-97. The total length of
transmission lines, today is over 5bn ckt
Kms (March, 1995) as compared to 29,271 ckt
Kms in 1950. However, this growth has not
been enough to meet the increasing
requirements, necessitated by the rapid
population growth and industrial
development.
The power sector has been
characterised by shortage of supply
vis-à-vis demand. In 1990-91, the country
faced peaking shortage of around 16% and
energy shortage of about 8%. The position
has gradually worsened with peaking shortage
touching 18% and energy shortage almost 12%
at the end of the 8th Plan (1997). Power
shortage has been identified as one of the
major constraints to India’s economic
development.
The infrastructure sector
was traditionally the preserve of the
government. However, recent budgetary
constraints has led to the realisation that
the government is no longer in a position to
meet the infrastructural requirements of the
country on its own. In tune with the policy
of liberalisation which was introduced in
the Indian economy and keeping in mind the
quantum of investment required, the
Government of India in 1991 decided to allow
the entry of the private sector into the
power sector. Private sector participation
was considered as the most viable solution
towards bridging the gap between the demand
and supply of electricity in India.
A number of policy
initiatives were undertaken to facilitate
and regulate the entry and operation of
private entrepreneurs in the power sector,
(see Table 1).
As a result to these
initiatives, a large number of projects have
been taken up by the private sector. The
electricity generated from these projects is
envisaged to be sold to the State
Electricity Board (SEB) under long term
contracts. A number of power purchase
agreements have been signed in almost all
the states in the country.
OVERVIEW OF POWER
PURCHASE AGREEMENTS (PPAs)
Parties. Under
Indian laws, a company which sets up a
generating station has to be a generating
company. A generating company is defined in
Section 2(4-A) of the Electricity Supply
Act, 1948 as “a company registered under the
Companies Act, 1956 and which has among its
objects the establishment, operation and
maintenance of generating stations”.
Generally, the power purchaser is the State
Electricity Board (SEB).
Term. The
concession period mainly depends upon the
proposed fuel for the project. For
coal-based projects, the period ranges from
25-30 years with one or two extensions of 10
years each; for liquid fuel based projects,
the concession period ranges from 15-20
years with one or two extensions of five
years each. The Government of India has
prescribed a maximum term (of 15 years) for
diesel engine generating stations.
Tariff. Tariff for
power is comprised of two parts: fixed
(capacity) charges and variable (energy)
charges. Fixed charges consist of O&M
expenses, debt service obligations, return
on equity, etc., while variable charges
consist of expenses pertaining to fuel,
including cost of fuel, transportation
charges and taxes and duties levied on fuel.
O&M charges are escalated yearly on the
basis of price index. Fuel price risk is
generally passed on the purchaser.
Protection against
foreign exchange fluctuations is provided to
the seller for foreign debt and foreign
equity. However, in the case of the recent
competitive bid projects foreign exchange
risk for foreign equity is generally borne
by the seller.
Take or pay. The
power purchaser usually guarantees the
offtake of electricity based on a plant load
factor, which could vary between 68.5% to
90%.
Liquidated damages.
The seller has to guarantee supply of
electricity by a fixed date: any delay
entails the payment of liquidated damages to
the purchaser. However, if the delay in
commissioning is due to any default of the
purchaser, the seller is compensated for the
same by way of payment of fixed charges,
thereby covering the debt service
obligations and other fixed costs of the
seller.
Any shortfall in
contracted capacity entails a proportionate
reduction in the fixed charge component of
tariff. In some cases the seller is also
liable to pay liquidated damages to the
buyer.
Security package.
Considering the financial condition of the
power purchaser, the security package
generally consists of: Letter of Credit,
Escrow Account, the State Government
Guarantee and Direct Sale to consumers or
the regional grid (in the case of SEB
default). Counter Guarantees from the
Central Government have been discontinued.
Fuel. The power
producer is responsible for arranging fuel
for the project, through an arrangement with
the government monopolies. In some cases,
especially recently with liquid fuels, the
government has allowed the power producers
to directly procure fuel from abroad. Since
fuel costs, in most cases, are passed
through to the purchaser, the purchaser
generally has a right to approve the fuel
supply contracts.
Force majeure. The
force majeure provisions are generally
classified into two categories: natural and
political. No compensation is provided for
natural force majeure affecting either
party, though in some PPAs limited
compensation is provided to the developer
for natural force majeure affecting the
purchaser. For political force majeure
events, the developer is compensated by way
of payment of fixed charges.
Assignment of PPA.
Assignment of the PPA and other contracts
including the security package, in favour of
the lenders is permitted. Even creating a
charge on the land, which in the majority of
cases is taken on lease from the state
government, in favour of the lenders, is
allowed in most cases. Assignment of the PPA
in favour of any third party (other than the
lenders) generally requires the consent of
the purchaser.
Dispute resolution.
Arbitration is currently the most favoured
mode of dispute resolution. Earlier, most
arbitration agreements provided for
arbitration outside India under foreign law,
since enforceability of “foreign awards” in
India was easy as compared to domestic
awards. With the new Arbitration and
Conciliation Act, 1996, based on the
UNCITRAL Model Law, more and more PPAs
provide for arbitration governed by domestic
law. The new Act has reduced the
jurisdiction of the courts in the
arbitration proceedings and the award,
though the Act is yet to be tested in the
courts.
Termination and
buy-out. In the case of a default by the
power producer, lender cure periods are
provided. The purchaser has an option to buy
the project in the event of termination due
to a default by the seller. Similarly, the
producer has the option to sell the project
to the purchaser (SEB) in the event of
termination of the PPA due to default by the
purchaser. Generally, upon expiry of the
term of a PPA, buy-out of the project by the
SEB, at a price base don depreciated
replacement cost, is provided under the PPA.
CLEARANCES
One of the reasons often
cited for the delays encountered while
setting up private projects in India, is the
numerous clearances and permits which are
required to be obtained. Approximately, over
50 clearances and permits are required to be
obtained. Approximately, over 50 clearances
and permits are required. However, most of
the clearances are routine in nature.
Two of the most important
clearances are: Techno-economic clearance
from the Central Electricity Authority (CEA)
and the Environmental Clearance.
Techno-economic
clearance from CEA. Under Section 29 of
the Electricity Supply Act, 1948, projects,
involving capital expenditure above certain
limits require clearance from the CEA. CEA
clearance is a two stages process: at the
first stage CEA grants “in principle
clearance” to the project and the final
“techno-economic clearance” is granted at
the second stage. The cost limit of this
project has been fixed at:
-
Rs. 1,000 crores (US$
250m approximately) – for generation
projects selected through competitive
bidding.
-
Rs. 500 crores
(US$125m approximately) – for schemes
for renovation and modernisation of
existing power plants.
-
Rs. 100 crores (US$
25m approximately) – for other schemes
(including generation projects selected
otherwise than through competitive
bidding).
Techno-economic clearance
involves a comprehensive review of the
project involving both its technical and
economic parameters. The project cost is
comprehensively reviewed by the CEA.
Environmental
clearance. Some of the key environmental
legislation in India includes:
-
the Environment
(Protection) Act, 1986;
-
the Air (Prevention
and Control of Pollution) Act, 1981;
-
the Water (Prevention
and Control of Pollution) Act, 1974;
-
the Forest
(Conservation) Act, 1980; and
-
the Wildlife
(Protection) Act, 1972.
The Ministry of
Environment and Forests, of the Government
of India grants the final environment
clearance to a project. The Central
Government has transferred to power to state
governments for granting environmental
clearance to certain categories of thermal
power plants, both utility and captive. Such
plants include:
-
Coal-based plants up
to 500 MW using fluidised bed technology
subject to sensitive area restrictions.
-
Coal-based plants up
to 250 MW using conventional
technologies.
-
Gas/naphtha based
plants up to 500 MW.
-
Captive plants up to
250 MW (both coal and gas/naphtha based)
coming up separately and not along the
main industry.
-
All cogeneration
plants irrespective of their installed
capacities.
However, any project
proposed to be located within the radius of
25 kms from the boundary of reserved
forests, ecologically sensitive areas, which
may include national parks, sanctuaries,
biosphere reserves, critically polluted
areas, and within 50 kms of an interstate
boundary, shall require environmental
clearance from the Central Government.
Detailed procedure for
seeking environmental clearance has also
been notified.
Foreign investment
approval. The power sector has been
identified as a “high priority industry”.
There is no ownership restriction upon the
quantum of foreign equity; even 100% foreign
equity is permitted, depending upon the
merits of the case. Proposals involving
foreign equity up to 74% are cleared on an
automatic basis by the Reserve Bank of
India. Proposals involving foreign equity
above 74% are approved by the Government of
India on a case-by-case basis.
CAPTIVE/COGENERATION
PLANTS
In view of the delays in
the implementation of the independent power
projects, the Government of India has denied
to actively encourage the setting up of
captive and cogeneration projects. A policy
on cogeneration projects has also been
published. The SEBs provide wheeling and
banking services to such
captive/cogeneration projects. Surplus power
from these projects is bought by SEB at a
mutually negotiated tariff.
The process of according
clearance to captive/cogeneration projects
has been simplified. Proposals for captive
power/cogeneration plants require the
approval of the SEB. In cases where the
capacity of the generating station exceeds
25 MW, the SEB has to simply refer the
proposal to the CEA for consultation under
Section 44 (2A) of the Electricity (Supply)
Act, 1948. A detailed examination of the
project by CEA as undertaken for purposes of
techno-economic clearance, is unnecessary
for such plants.
Generating companies
setting up captive power plants for the
exclusive use of an industrial unit or a
group of industrial units, need to be
selected through international competitive
bidding. However, such plants would not be
allowed to sell their surplus energy to the
SEB.
RESPONSE
Around 128 power projects
(requiring CEA clearance) for a total
capacity of 69,021 MW involving an
investment of about Rs. 2,547 bn (US$64bn
approximately) are proposed to be set up. In
addition, there are several projects (e.g.
small liquid fuel-based short gestation
projects) being set up by the private sector
with the approval of the state government
itself (i.e. they do not require CEA
approval).
In spite of the figures
indicated in Table 2 we cannot ignore the
issues encountered by the private developers
while setting up projects in India. Apart
from the usual delays in the grant of
clearances, the problems that arose in the
grant of clearances, the problems that arose
in the grant of fuel linkages for the liquid
fuel projects and the delays in the
finalisation of the model fuel supply
agreement are well known.
Apart from the policy on
setting up for new power plants by the
private sector, a detailed policy on private
sector participation in Renovation and
Modernisation (R&M) of existing plants, both
thermal and hydel, has also been published.
Three options for private investment are
envisaged:
-
Lease, rehabilitate,
operate and transfer (LROT);
-
Sale of plant; and
-
Joint venture between
SEBs and private companies.
However, R&M of existing
plants has not proved to be an attractive
investment opportunity for the private
sector.
Until now, the major
thrust of the government’s efforts has been
concentrated on power generation.
Transmission and distribution has not
received as much attention as one would have
hoped. The Bill admitting private parties in
the transmission sector was introduced in
the Parliament, which, however, could not be
passed due to the dissolution of the House.
It is expected that permitting private
sector investment in the transmission sector
would be one of the first initiatives to be
taken by the new government at the Centre.
CONCLUSION
A National Power Plan was
prepared by CEA in 1996-97, spanning a
15-year period up to the end of the 11th
Plan (2011-12), based on the 15th Electric
Power Survey. In the Plan, projects
amounting to 153,783 MW have been identified
as the need based requirements for the 15
year period. Based on the capacity addition
requirements, funds required for the
generation component of the National Power
Plant have been assessed at Rs. 6,000 bn
(US$150bn approximately). Keeping in mind
the funds required for the transmission and
distribution components a total of Rs.
10,000 bn (US$250bn approximately) has been
assessed for the power sector as a whole.
In view of the large
investment required for fufilling the need
based requirement of the country in the near
future. India’s power sector will continue
to be an area of opportunity for investment
by the private sector. There is a growing
realization in the government that the bulk
of the additional generation requirement cod
be achieved by renovating and modernizing
the existing plants. Hence, it is expected
that there may be a shift in focus from
greenfield projects to existing plants.
Transmission of the power
generated from the proposed private sector
projects would require huge investments in
the transmission sector. The enactment of
law permitting private participation in the
transmission sector is expected to
kick-start this process. In the coming yeas,
the private sector would focus its attention
or transmission and distribution. The
lessons learnt during the past seven years
would hopefully shorten the gestation
periods of such projects.
Table 1: Broad
features of current power supply
|
1 |
The Indian
Electricity Act, 1910 and the
Electricity (Supply) Act, 1948, the
two principal Acts governing the
electricity sector in India have
been amended with a view to
modernise the legal, administrative
and financial environment in order
to accommodate private enterprises
in the power sector.
|
|
2 |
Private sector
investors are now able to set up
thermal projects (coal/gas/naphtha
and other liquid fuel based
product), hydel projects and
wind/solar energy projects of any
size. |
| 3 |
Private sector
companies can set up enterprises to
operate either as licensees or as
generating companies. |
| 4 |
All private sector
companies are allowed a debt equity
ratio of up to 4:1. |
| 5 |
The promoters equity
contribution should be at least 11%
of the total outlay. |
| 6 |
To ensure that
private sponsors commit resources to
the sector, not less than 60% of the
total outlay for a project must come
from sources other than Indian
public financial institutions. |
| 7 |
Up to 100% foreign
equity participation is permitted
for projects set up by foreign
private investors. |
| 8 |
Capital Cost Limits
for power projects requiring Central
Electricity Authority (CEA) approval
has been enhanced. |
| 9 |
A guaranteed rate of
return of up to 16% will apply. |
| 10 |
In certain cases,
tariffs can be fixed in deviation of
norms stipulated in the Government
of India (GOI) tariff notification
of March, 1992. |
| 11 |
A five year tax
holiday has been allowed. |
| 12 |
The rates for
depreciation in respect of certain
assets have been rationalised. |
| 13 |
Duty on import of
power equipment has been reduced to
20% and this reduced rate has also
been extended to machinery required
for renovation and modernisation of
existing power plants. |
| 14 |
Liberalisation of
access to external commercial
borrowings for power sector
borrowers. |
| 15 |
In order to encourage
captive generation, including
cogeneration, power plants,
guidelines have been issued to state
governments recommending the
creation of a mechanism for early
clearance of such proposals and also
to ensure effective measures such as
purchasing or wheeling of surplus
power from such plants. |
| 16 |
The excise duty on a
large number of capital goods and
equipment in the power sector has
been reduced. |
|